Earliest Completion Time for Dependent Kernel Launches
Last updated: November 29, 2026
Quick Overview
You are given durations for GPU kernels and a list of dependencies (a, b) meaning b may start only after a finishes. Assuming unlimited parallel hardware, return the earliest time all kernels finish and each kernel's earliest start time, or report a cycle.
AMD
November 29, 20260
0
0 solved
You are given durations for GPU kernels and a list of dependencies (a, b) meaning b may start only after a finishes. Assuming unlimited parallel hardware, return the earliest time all kernels finish and each kernel's earliest start time, or report a cycle.
An onsite coding round in the style of AMD HIP runtime and graph teams, where HIP graphs and multi-stream applications form a dependency DAG and the critical path bounds achievable latency. The interviewer checks topological sorting, longest path in a DAG, and cycle detection.
What the Interviewer Expects
- Model the problem as longest path in a DAG
- Use Kahn's algorithm with in-degrees
- Propagate start time as the max finish time of predecessors
- Detect cycles when not every node is processed
- Return the overall finish as max start plus duration
- Give O(V + E) complexity
Key Topics to Cover
How to Approach This
- Clarify input constraints and edge cases before writing code.
- Walk through your approach verbally and confirm with the interviewer before coding.
- Start with a brute force solution, then optimize. Mention time and space complexity.
- Test your solution with examples, including edge cases like empty input or duplicates.
- Consider common patterns: sliding window, two pointers, hash map, BFS/DFS, dynamic programming.
Possible Follow-up Questions
- How would you recover the actual critical path, not just its length?
- How does the answer change with only two hardware queues?
- How would you incrementally update finish times when one kernel's duration changes?
- Where do implicit dependencies come from in real multi-stream code?
Sharpen Your Skills on Codemia
Practice similar problems with our interactive workspace, get AI feedback, and track your progress.
Practice DSA ProblemsSample Answer
Requirements
Input: durations (list, kernel i has durations[i]) and deps, pairs (before, after). Output: (finish_time, start_times) or None if the dependencies contain a cycle. Kernels with no predeces...
High-Level Design
Earliest start of kernel v is the max over predecessors u of start[u] + durations[u]. That is a longest path computation, which is easy on a DAG in topological order. Kahn's algorithm gives that ord...