Expected Imbalance Cost From a Normally Distributed Demand Forecast

Last updated: November 29, 2026

Quick Overview

A supplier's forecast error for one settlement period is normal with mean 0 and standard deviation 20 MWh; being short costs 30 pounds per MWh over the contract price and being long costs 10 pounds per MWh. Compute the expected imbalance cost of hedging the forecast exactly, then find the cost-minimising hedge and its expected cost.

Fuse Energy
Statistics & Math
Quantitative Researcher
Fuse Energy
November 29, 2026
Quantitative Researcher
Phone Screen
Statistics & Math
Easy

0

0

0 solved


A supplier's forecast error for one settlement period is normal with mean 0 and standard deviation 20 MWh; being short costs 30 pounds per MWh over the contract price and being long costs 10 pounds per MWh. Compute the expected imbalance cost of hedging the forecast exactly, then find the cost-minimising hedge and its expected cost.

Fuse buys power ahead of delivery for its retail book and pays imbalance prices for any mismatch, so traders and quants reason about forecast error in money terms daily. The phone screen checks comfort with expectations of truncated normals and spotting the newsvendor structure.

What the Interviewer Expects
  • Write the cost as an asymmetric piecewise linear function of the error
  • Use $E[\max(Z,0)] = \sigma/\sqrt{2\pi}$ for a centred normal
  • Recognise the newsvendor critical ratio for the optimal hedge
  • Compute the optimal quantile and resulting expected cost
  • Explain intuitively why you over-hedge
Key Topics to Cover
Normal distribution
Expected value
Newsvendor problem
Imbalance pricing
Asymmetric loss
How to Approach This
  1. Define your hypotheses (H0 and H1) clearly before performing any test.
  2. Calculate required sample size BEFORE running an experiment, using power analysis.
  3. Remember the Central Limit Theorem: sample means become approximately normal with large n.
  4. Watch for Simpson's paradox. Always segment data by key dimensions.
  5. Distinguish between statistical significance and practical significance.
Possible Follow-up Questions
  • How does the answer change if the error distribution is fat-tailed?
  • Imbalance prices are correlated with your error (everyone is short on a cold day). How does that change the hedge?
  • How would you estimate sigma per period from historical forecasts?
  • What if you can trade intraday at a smaller spread closer to delivery?
Sharpen Your Skills on Codemia

Practice similar problems with our interactive workspace, get AI feedback, and track your progress.

Browse Statistics Questions
Sample Answer
Clarify

Let actual demand be D=D^+εD = \hat D + \varepsilon with ε∼N(0,σ2)\varepsilon\sim N(0,\sigma^2), σ=20\sigma=20. If we buy qq, cost is cs (D−q)++cl (q−D)+c_s\,(D-q)^+ + c_l\,(q-D)^+ with cs=30c_s=30 (short), cl=10c_l=10 (long). Prices a...

Approach

Case 1: q=D^q=\hat D. Then cost is csε++clε−c_s\varepsilon^+ + c_l\varepsilon^-, and for a centred normal E[ε+]=E[ε−]=σφ(0)=σ/2πE[\varepsilon^+]=E[\varepsilon^-]=\sigma\varphi(0)=\sigma/\sqrt{2\pi}. Case 2: choose qq to minimise...