Recovering an ERP Go-Live That Is Slipping Six Weeks Before Cutover

Last updated: November 29, 2026

Quick Overview

You are the delivery manager on a client's SAP S/4HANA rollout. Six weeks before cutover, integration testing shows a high defect count and two key interfaces are late. Walk me through how you lead the team and the client through the next six weeks.

Deloitte
Behavioral & Leadership
Engineering Manager
Deloitte
November 29, 2026
Engineering Manager
Behavioral Round
Behavioral & Leadership
Medium

0

0

0 solved


You are the delivery manager on a client's SAP S/4HANA rollout. Six weeks before cutover, integration testing shows a high defect count and two key interfaces are late. Walk me through how you lead the team and the client through the next six weeks.

Manager and senior manager interviews at Deloitte lean on delivery scenarios, because large ERP and modernization programs are where engagements succeed or fail. The interviewer is probing judgment under pressure: how you get the real picture, make a go or no-go call with the client, and keep a tired team effective.

What the Interviewer Expects
  • Establishes facts quickly: defect severity, burn-down trend, critical path
  • Sets explicit go-live criteria agreed with the client
  • Reprioritizes and adds capacity where it actually helps
  • Communicates transparently with client leadership and their own partner
  • Prepares a contingency or phased cutover plan
  • Watches team health and avoids burning people out
Key Topics to Cover
delivery leadership
go/no-go criteria
risk management
stakeholder communication
ERP cutover
team health
How to Approach This
  1. Use the STAR method: Situation, Task, Action, Result.
  2. Be specific about YOUR actions, not just the team outcome.
  3. Quantify your impact whenever possible (e.g., "reduced latency by 40%").
  4. Prepare stories for: conflict, failure, ambiguity, leadership, and technical trade-offs.
  5. Show growth mindset. Explain what you learned and how you changed your approach.
Possible Follow-up Questions
  • The client sponsor insists on the original date for a board commitment. What do you do?
  • How do you decide whether adding people will help or hurt?
  • What would make you recommend a no-go?
  • How do you handle a team member whose module keeps slipping?
Sharpen Your Skills on Codemia

Practice similar problems with our interactive workspace, get AI feedback, and track your progress.

Browse Behavioral Questions
Sample Answer
What They Are Probing

Whether you lead from data, not hope. A strong answer shows you can tell a client sponsor the truth, convert chaos into a short list of decisions, and protect both the client's business and your team....

Situation and Task

Treat it as a scenario, or tell a similar real one. Here: 410 open defects, 38 of them severity 1 or 2, burn-down flat for two weeks, the warehouse interface and the bank payment interface both two we...


Submit Your Answer