Simulate a Human Data Pipeline With Dependent Tasks
Last updated: November 29, 2026
Quick Overview
Tasks in an AI-training data project (writing, review, gold-set creation, audit) have durations, priorities and dependencies; with W identical experts, simulate list scheduling where free experts always start the highest-priority ready task, and return the makespan and each task's start and end, detecting cycles.
Micro1
November 29, 20260
0
0 solved
Tasks in an AI-training data project (writing, review, gold-set creation, audit) have durations, priorities and dependencies; with W identical experts, simulate list scheduling where free experts always start the highest-priority ready task, and return the makespan and each task's start and end, detecting cycles.
Project leads at a human-data company need to promise AI lab clients a delivery date for multi-stage work. The interviewer checks Kahn-style dependency tracking combined with an event-driven simulation, correct handling of simultaneous completions, and cycle detection.
What the Interviewer Expects
- Validates dependencies reference known tasks
- Combines in-degree tracking with a ready priority queue
- Uses an event heap of running tasks keyed by end time
- Releases all tasks that finish at the same time before scheduling
- Detects cycles by counting scheduled tasks
- States that greedy list scheduling is not optimal and why
Key Topics to Cover
How to Approach This
- Clarify input constraints and edge cases before writing code.
- Walk through your approach verbally and confirm with the interviewer before coding.
- Start with a brute force solution, then optimize. Mention time and space complexity.
- Test your solution with examples, including edge cases like empty input or duplicates.
- Consider common patterns: sliding window, two pointers, hash map, BFS/DFS, dynamic programming.
Possible Follow-up Questions
- How far from optimal can greedy list scheduling be, and what bound applies?
- How would you model experts with different domains or speeds?
- How would you use this simulation to answer: how many extra reviewers do we need to ship by Friday?
- What if durations are random? How would you estimate a P90 delivery date?
Sharpen Your Skills on Codemia
Practice similar problems with our interactive workspace, get AI feedback, and track your progress.
Practice DSA ProblemsSample Answer
Requirements
Input: tasks = {id: (duration, priority)}, deps = [(before, after)], workers = W. Any free worker takes the ready task with the highest priority, ties by id. A task is ready when all predecessor...
High-Level Design
Keep in-degrees and a children list. The ready set is a heap of (-priority, id). Running tasks sit in a heap of (end, id). The loop alternates two phases: fill every free worker from the ready hea...