Turn Around a Delivery Program That Is Over Budget and Late

Last updated: November 29, 2026

Quick Overview

You take over as delivery lead on a multi-team ERP modernization program that is three months behind, 25% over budget, and has an unhappy client sponsor. Walk through what you did, or would do, in your first 90 days.

Accenture
Behavioral & Leadership
Engineering Manager
Accenture
November 29, 2026
Engineering Manager
Behavioral Round
Behavioral & Leadership
Hard

0

0

0 solved


You take over as delivery lead on a multi-team ERP modernization program that is three months behind, 25% over budget, and has an unhappy client sponsor. Walk through what you did, or would do, in your first 90 days.

Delivery leads and senior managers at Accenture are judged on recovering troubled engagements while protecting both client relationship and margin. The interviewer checks diagnosis before action, honest re-planning, scope negotiation, team health and commercial awareness.

What the Interviewer Expects
  • Diagnoses root causes with data before changing plans
  • Resets the plan honestly with the client instead of promising to catch up
  • Negotiates scope, phasing or commercials with clear trade-offs
  • Addresses team structure, morale and key-person risk
  • Sets up leading indicators and a governance cadence
  • Shows commercial awareness about margin and change requests
Key Topics to Cover
Program recovery
Stakeholder management
Re-planning
Scope negotiation
Team health
Commercial management
How to Approach This
  1. Use the STAR method: Situation, Task, Action, Result.
  2. Be specific about YOUR actions, not just the team outcome.
  3. Quantify your impact whenever possible (e.g., "reduced latency by 40%").
  4. Prepare stories for: conflict, failure, ambiguity, leadership, and technical trade-offs.
  5. Show growth mindset. Explain what you learned and how you changed your approach.
Possible Follow-up Questions
  • The client sponsor wants your firm to absorb all the overrun. How do you handle it?
  • A strong but abrasive tech lead is part of the problem. What do you do?
  • How do you know at day 30 whether the recovery is working?
  • When would you recommend stopping the program?
Sharpen Your Skills on Codemia

Practice similar problems with our interactive workspace, get AI feedback, and track your progress.

Browse Behavioral Questions
Sample Answer
What They Are Probing

Judgment under pressure: do you diagnose before acting, tell the truth to a frustrated client, make hard scope and people decisions, and keep the engagement commercially viable? They want structure an...

Situation and Task

I inherited a program moving a manufacturer's finance and procurement from an on-premise ERP to a cloud ERP: five teams, about 60 people across two delivery centers. It was three months late and 25% o...